October 29, 2026
On the eighth tee at the Bald Head Island Club, the ocean and Old Baldy are both in view. That view hasn't always been there. During the course's last renovation, the tees at No. 8 were raised ten feet so golfers could see the water and the lighthouse, according to a StarNews account of that renovation.
That is the best guide to the year ahead. On Monday, November 9, the back nine closes for the Club's Golf Course Rejuvenation Project. The architect leading the work has said the routing will stay as it is. That makes this the second time someone has rebuilt George Cobb's course without moving its holes, and the first time shows what that kind of project tends to change.
The Club's maintenance and closings page lays out a projected schedule. The Club says every date on it is subject to change.
| Projected date | What happens |
|---|---|
| Monday, November 9, 2026 | Back nine, holes 10 through 18, closes |
| Monday, January 4, 2027 | Front nine, holes 1 through 9, closes |
| By June 20, 2027 | Construction expected to be complete |
| Summer 2027 | Grow-in and course preparation |
| October 5, 2027 | Target reopening |
If those dates hold, the front nine stays open for about eight weeks after the back nine closes, carrying play through the holidays. The back nine would be out for about eleven months. From January through early October 2027 the whole course would be closed, roughly nine months with no holes in play. Since construction is expected to finish in June, about a third of that closure is grow-in, when new turf gets established before anyone plays on it.
The page also says the work is meant to improve "course infrastructure, playability, and long-term turf health." That covers both what's underground and what's on the surface, and the Club hasn't published a more detailed list of the work.
The Club's golf page says the course came before the Club. Cobb designed it, and it opened in 1974, winding through maritime forest, around freshwater lagoons and along a dune ridge. StarNews points out that Cobb also designed East Lake and Quail Hollow, plus the nearby Oak Island and Surf courses.
By the late 2000s, the course was showing its age. Robert Norton, then the general manager, told StarNews that "after more than 35 years of strong ocean winds, intense summer suns and thousands of rounds of play," the course "was getting a bit tired." Wilmington architect Tim Cate came over in 2010 to build tee complexes and rebuild the greens. After studying Cobb's original plans, he decided the project had to be bigger. In the StarNews piece, Cate put it this way:
"The mechanics were way off. There were no landing areas, no second doglegs, greens were not designed in a fashion that allowed for any strategy."
The finished project cost more than $4 million, StarNews reported. Even at that size, Cate kept Cobb's routing. Here is what changed, as StarNews described it:
The Club's own summary is that Cate replaced "acres of turf with natural areas" and expanded the views. That is a lot of change for a project that left every hole where Cobb put it. The holes kept their places, and the land around them was opened up so you could see it.
The Club names Andrew Green as the architect leading the new project. In a video the Club uploaded in September 2025, filmed on the 18th hole, Green said: "We're not going to reroute the golf course. We're not going to play the golf course backwards. We're really looking at the corridors and the golf holes that you have and how to make them better."
In the same video, Green called the property "probably the greatest golfing ground between South Florida and Long Island." He listed his past work, including Oak Hill in Rochester, which hosted the 2023 PGA Championship, and, most recently, East Lake Golf Club in Atlanta. Since StarNews credits Cobb with East Lake, the architect now working on Bald Head has recently worked on another course that traces back to Cobb.
Green also mentioned the logistics. "Building a golf course on an island, not the easiest thing in the world to do," he said, adding that the team thought it could find an efficient way forward. Note when he said this. In that 2025 video, he described the master plan as "a pretty decent draft" that still needed revisions, and he said members would get to review it and give feedback. So his statements are his intent at the draft stage, not a description of the final plan.
The Bald Head scope hasn't been made public. Green's work at Oak Hill shows what his projects have involved on a different course, and that's the only reason it's described here.
GCM, the golf course superintendents' magazine, covered the Oak Hill project in May 2023. It described a yearlong restoration of the East Course beginning in 2019 that touched every hole. Green called it a "sympathetic restoration," which he explained as blending the original designer's intent with how the game is played now. The work there included:
Oak Hill is a different property, built for a different championship, and nothing on that list should be read as Bald Head's plan. What the two projects share is the approach: keep the existing layout, change what's inside it, and take about a year to do it. Bald Head's projected schedule is also about a year.
The Club hasn't posted any closure-period details on its public pages. That includes reciprocal play at other clubs, temporary holes, and whether the practice range stays open during construction. The Golf Shop at 910.457.7310 can answer questions, and the maintenance page is where updates are posted. The Club also says that in late fall and winter, openings and tee times depend on the weather, which will matter while only nine holes are open.
For golfers who want to keep playing across the river, two mainland courses take public play:
Back on the island, the course still runs through the maritime forest with its hundreds of sabal palms. The Club notes that Bald Head is the northernmost place on earth where these palms grow naturally. Foxes, herons, egrets and ospreys show up on the course all the time, and so does the occasional alligator. If the work follows the pattern of the last rebuild, the course that reopens, targeted for October 5, 2027, will play the same holes in the same order, with the land around them changed.
If a year-long change at the Club has you rethinking how you use your Bald Head home, whether you're planning seasons around the closure or weighing a sale or purchase timed to the reopening, I'd be glad to talk it through with you. Barbara Adams offers patient, numbers-first guidance for decisions like these. Schedule a confidential consultation.